Pooncarie Road – project update

Wentworth Shire Council recommenced earthworks on the final 26.5 kilometres of unsealed road between Pooncarie and Menindee in July 2023, following 8 months of flood related delays.

The $9.2 million project is jointly funded on a 50:50 basis with the Australian Government and NSW Government under the Growing Local Economies Fund with Office of Regional Development.

The upgrade allows road users to access the road in all weather conditions, removing over 600km of road detours when the road is impacted by wet weather-related road closures.

Bitumen sealing has now been completed, with guide posts, linemarking and signage underway.

The project is due for completion by the end of November.

default