Mourquong Water Main Extension project update

Council has received many requests from residents in Mourquong for the provision of filtered water.

After several proposals and feasibility studies, Council approved approximately 1.3km of a filtered water main to service 9 properties in Stage 1 of the project.

The project consists of an under road bore, under pressure tapping of the rising main, installation of pipe and property connections.

Council engaged the services of Urban H2O to undertake the work

The project is almost complete with testing and commissioning to be completed prior to Christmas.

Buronga Pump Track project update

Works commenced last week on the construction of a new sealed Pump Track at the Buronga Riverfront, west of the George Chaffey Bridge near the Discovery Caravan Park.

The track will be around 150m in length and will create an environment for the community to enjoy, whilst challenging their varying levels of skill through rollers and berms.

The project is funded under the Local Roads & Community Infrastructure Program and will be completed in December 2021.

Dareton Travellers Rest project update

Wentworth Shire Council and Dareton Community Action Team (CAT) have worked together to provide the town a new Traveller’ Rest, which is now nearing completion.

The project will provide a permanent memorial with names to commemorate those from the Dareton and Coomealla District who served their country in wartime.

With the town’s existing Anzac Memorial site unsuitable for the listing of names a new site in Tapio Park was chosen as an extension of the registered war memorial site.

Works were planned by Council in conjunction with the CAT and the Coomealla Memorial Sporting CLub.

The CAT proposed the construction of the Travellers Rest pergola, interpretive panels, new granite war memorial and associated pathways and have been successful in securing funds from the club as well as further government funding to complete the project.

Local historian and author Malcolm Williams provided the story and images to be used on the panels.

Works on stage one of the project will be completed by Christmas with placement of the new granite memorial expected to be completed in January 2022.

Wentworth Showgrounds Sewer Upgrade

With support from the Crown Reserve Improvement Fund’s Showgrounds Stimulus Program Council is undertaking works at the Wentworth Showgrounds to replace multiple septic systems with a combination of gravity and pressure sewage network to cater for the rise in usage of the facilities.

These works include:

  • Installation of a gravity sewer system;
  • Installation of a central Sewer Pump Station to connect to the existing rising main;
  • Decommissioning of old septic tank systems throughout the Showgrounds and connecting plumbing to the network.

Council engaged the services of MH2 Engineering & Architectural Services for the design with works undertaken by Waters Excavations PTY LTD.

Construction commenced on 16 November and is well underway with just over 100 metres of pipe and 5 Ezipits installed so far.

The project concludes in early February with the installation of the sewer pump station, electrical switchboard, testing and commissioning.