Anabranch Mail Road Resheeting Upgrade

Arumpo Road sealing has commenced
Contractors commenced sealing the first 13 kilometre section of Arumpo Road on Monday 18 November 2024.

Key project details:
24.52km section of road upgrades including 2 x 100mm sub base layers with 25 pieces of plant utilised on the project
Works commenced in June 2024
Expected completion of March 2025
Funding consists of $5 million (Australian Government) and $1.25 million (NSW Government)

NSW Youth Week Outdoor Movie Night

Thank you for joining us! Wentworth Shire Council extends its thanks to everyone who attended the NSW Youth Week Outdoor Movie Night on Friday 11 April. The event, organised by students of Coomealla High School with support from Council, was a celebration of youth, creativity and community. We value your feedback. By completing the short […]